After more than four decades, Serbia will get another pump storage hydro power plant Bistrica. The preparation of technical documentation will be completed by the end of the year, and the preparatory works will begin next year.
Located in the Lim river watershed near existing hydropower plants, it will feature four units with a combined installed capacity of 680 MW. The total estimated cost for the project is €1.2 billion.
The construction of the pumped-storage hydropower station Đerdap3 with a capacity of 2,400 MW and the Bistrica hydropower station with a capacity of 680 MW has been planned for decades.
This project involves the construction of the Bistrica Pumped Storage Power Plant to enhance energy production and storage in Serbia.
The construction of the pumped-storage hydropower station Đerdap3 with a capacity of 2,400 MW and the Bistrica hydropower station with a capacity of 680 MW has been planned for decades.
The Government of Serbia adopted the special purpose spatial plan for a system that would consist of planned pumped storage hydropower plant Bistrica and existing hydropower plant Potpeć. It is another step toward the materialization of the currently most important project in Serbia''s energy sector.
The justification study for the pump-storage hydropower plant Bistrica has been completed, with the final phase now focusing on obtaining location permits and preparing project documentation for relocating sections of state roads, transmission lines, and water pipelines.
Serbia has completed the feasibility study for pumped storage hydropower plant Bistrica and the cost is estimated at more than EUR 1 billion, Minister of Mining and Energy Dubravka Đedović said after speaking to
Serbia has completed the feasibility study for pumped storage hydropower plant Bistrica and the cost is estimated at more than EUR 1 billion, Minister of Mining and Energy Dubravka Đedović said after speaking to Ambassador of Japan Akira Imamura about joint energy and environmental projects.
Representatives from Serbia''s state-owned power utility EPS, local authorities, and non-governmental organizations held a presentation in Nova Varoš to discuss the construction of the Bistrica pumped-storage hydropower plant.
The Government of Serbia has adopted a special purpose spatial plan for the 628 MW Bistrica pumped-storage hydropower project in western Serbia.
The construction of the pumped-storage hydropower station Đerdap3 with a capacity of 2,400 MW and the Bistrica hydropower station with a capacity of 680 MW has been planned for decades.